Installation Instruction of BSD Resistance Reducing Agent2019/03/27Installation method and quantity instruction: 1. Powder quantity: 1) Vertical installation:Each meter of Ground rod or Chemical ground rod need about 25kg2) Horizontal installation:Each meter of Groun...
How to install BSD Ground rod?2019/03/27Note:If the Earthing rod needed length<=3000mm, use the earthing rod one pointed, strike deep directlyIf the Earthing rod needed length >3000mm, strike down the eathing rod one pointed first,the...
BSD Environmental Protection Exothermic Welding Flux User Manual2019/03/27The product is new developed environmental protection exothermic welding Flux, easy ignite, not volatile, can be stored up to 5 years.Exothermic Welding Flux Instruction 1. Put the welding Flux into t...
Installation Instruction of BSD Chemical Ground Electrode System2019/03/27The installation procedure of BSD Chemical Ground Electrode System:1. Borehole or dig pit:If vertical type BSD Chemical Ground Electrode System, should drill a holl first.Diameter should about 160mm; ...